GC Solar 22,70 GW GD Solar 49,91 GW
Politics & Regulation

Battery regulations suffer another postponement in ANEEL

Request for review delays decision and broadens debate on costs, tariffs, and regulatory framework.

Canal Solar - Battery regulation suffers another postponement in ANEEL

Willamy Frota (left) and Fernando Mosna (right), directors of ANEEL. Photo: ANEEL/ Flickr

Regulation of battery energy storage systems (BESS) has been postponed again. ANEEL (National Electric Energy Agency), after a new request for review, this time presented by director Willamy Frota.

The decision, taken at a meeting this week, once again halts the completion of a process considered strategic for the modernization of the electricity sector.

The postponement comes at a time of increasing demand for storage solutions, especially given the growth of renewable energy sources and recurring episodes of generation restrictions.

Motivations

In justifying the request for a review, Willamy Frota indicated the need to deepen the technical and legal analysis of the issue, based on the points raised in the dissenting opinion of director Fernando Mosna.

Frota also reported that he intends to conduct a new consultation with the Federal Prosecutor's Office. ANEEL and to engage in dialogue with the technical teams and advisors of the other members of the board.

Among the factors that motivated the postponement are the complexity of the subject and its impacts on the functioning of the electrical system, including issues related to curtailment and the integration of new technologies.

The decision also follows the agency's internal procedure, which provides for a collective review of the process, extending the time needed for a final decision.

Mosna vote

The dissenting opinion of director Fernando Mosna, which forms the basis of some of the discussions, proposes significant changes to the model originally presented in the public consultation. The main objective is to reduce costs and eliminate barriers to the adoption of batteries in the electrical system.

One of the key changes is the elimination of the so-called "dual tariff." According to the director's proposal, storage systems would only pay for grid use when energy is injected into the system, and not also when charging the batteries.

The argument is that the stored energy is not intended for final consumption, but for temporary displacement for later reinjection into the system. Another point is the increased flexibility of the MUST (System Usage Amount).

Mosna proposes allowing an immediate reduction of up to 30% for agents that install storage systems associated with generation, in contrast to the previous rule that provided for a gradual reduction over six years.

The ruling also addresses the TFSEE (Electricity Services Inspection Fee), arguing that there is no legal basis for charging it on storage systems until there is specific regulation for this category.

Furthermore, adjustments were made to the definition of closed-cycle reversible power plants, with the aim of clarifying their regulatory framework and avoiding ambiguities.

Long process

The regulation of energy storage in ANEEL It has been under discussion since Public Consultation No. 39/2023, but has faced successive postponements.

The process has been stalled since August 2025, when Mosna himself requested an initial review, raising concerns about the proposed tariff model.

Since then, changes to the legal framework (such as the enactment of Law 15.269/2025) have required additional technical revisions, prolonging the debate.

The Agency's technical areas maintained a favorable understanding regarding the charging of fees for both loading and unloading, a position that differs from the proposal presented in the dissenting opinion.

The process also involves adjustments to existing regulations and tariff procedures, as well as the need for adaptations to the company's own internal systems. ANEEL.

With the new request for review, the definition of rules for energy storage remains without a deadline for completion, maintaining market expectations for a regulatory framework considered essential to enable investments in batteries in the country.

all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.

Antonio Carlos Sil
About the Author
Antonio Carlos Sil

Antonio Carlos Sil is a journalist graduated from FMU/FIAM. He worked as a reporter for Brasil Energia, in addition to providing services to Agência Estado, Exame and Canal Energy. Worked in communications consultancies for CPFL Energia, CESP and AES Tietê. Has covered the electricity sector since 2000. Has experience covering events such as energy auctions, conventions, lectures, fairs, congresses and seminars.

Comments (1)

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

  • Andrelino Carvalho

    A ANEEL Who is all this apparent bureaucracy protecting? What interests are behind this decision?
    It's certain that the citizen will be the one who loses out. Where are the representatives? Where is the Public Prosecutor's Office?

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.