• Friday, November 14, 2025
Facebook X-twitter Instagram Youtube LinkedIn Spotify
  • GC Solar: 17,95 GW
  • GD Solar: 41,3 GW
  • TOPCon Modules: $0,088/W
  • P-Type Cells: $0,034/W
  • N-Type Cells: $0,032/W
  • HJT Modules: $0,10/W
  • N-Type Wafer: US$0,128/pc
  • Polysilicon: US$ 19,00/kg
  • GC Solar: 17,95 GW
  • GD Solar: 41,3 GW
  • TOPCon Modules: $0,088/W
  • P-Type Cells: $0,034/W
  • N-Type Cells: $0,032/W
  • HJT Modules: $0,10/W
  • N-Type Wafer: US$0,128/pc
  • Polysilicon: US$ 19,00/kg
  • advertise here
  • About us
  • Expedient
logo site solar channel
  • News
    • energy storage
    • Market and Prices
    • Investments & Business
    • Policy and Regulation
  • Articles
    • Batteries
    • Photovoltaic structures
    • Photovoltaic inverters
    • Opinion
  • Renewable
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Events
  • Videos
  • Electric Vehicles
  • Consultancy
  • Recent
  • News
    • energy storage
    • Market and Prices
    • Investments & Business
    • Policy and Regulation
  • Articles
    • Batteries
    • Photovoltaic structures
    • Photovoltaic inverters
    • Opinion
  • Renewable
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Events
  • Videos
  • Electric Vehicles
  • Consultancy
  • Recent
  • News
    • Brazil
    • World
    • Technology and inovation
  • Articles
    • technicians
    • Opinion
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • Events
  • Videos
  • About Us
  • Advertise Here
  • CS Consulting
  • Canal VE
  • Recent
  • News
    • Brazil
    • World
    • Technology and inovation
  • Articles
    • technicians
    • Opinion
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • Events
  • Videos
  • About Us
  • Advertise Here
  • CS Consulting
  • Canal VE
  • Recent
logo site solar channel
Home / News / Check out the results of the planning for the electricity sector until 2029

Check out the results of the planning for the electricity sector until 2029

Study, released by ONS, predicts total investments of R$7,6 billion
Follow on Whatsapp
  • Photo by Mateus Badra Mateus Badra
  • December 30, 2024, at 09:17 AM
4 min 1 sec read
Check out the results of the planning for the electricity sector until 2029
The national electricity grid has around 90% of its energy generated by renewable sources. Photo: Freepik

The ONS (National Electric System Operator) released, last Friday (27), the results of the Executive Summary of the Medium-Term Electric Operation Plan of the National Interconnected System – PAR/PEL 2024 for the period 2025 to 2029.

  • Join the Community Canal Solar on WhatsApp

The set of works indicated in the 2025-2029 cycle includes approximately 1.260 km of new transmission lines, in addition to 14.750 MVA of new transformers in new and existing substations. The estimated investments for these works are R$7,6 billion, of which R$5,8 billion are new projects.

The expansion of exchange limits between subsystems is one of the points highlighted in the study. The export capacity from the North/Northeast regions to the Southeast/Central-West regions, during the system's peak period, could increase by 30% by the end of 2029, rising from 15.600 MW, estimated for January 2025, to 20.500 MW. 

Export capacity from the Southeast/Central-West to the South is expected to increase by around 20% over the same period: from 10.500 MW (January 2025) to 12.500 MW (December 2029). The increase in exchange capacity is a positive factor for greater use of non-hydro renewable generation available in the Northeast region.

The PAR/PEL 2024 Executive Summary also addresses one of the main transformations in the planning and operation of the SIN: the increased participation of MMGD (micro and mini distributed generation). 

MMGD's installed capacity will surpass the 2024 GW mark in 33 and is projected to reach over 49 GW in 2029, which will consolidate it as the second largest source of generation in the country. The expansion of MMGD imposes considerable challenges on the operation of the electrical system, including the need for greater operational flexibility, management of constraints in the transmission network and support for the dynamic performance of the system.

SIN reservoirs reach 50% storage after heavy rains, says ONS

Impact of MMGD

The document also highlights the impact of MMGD on the SIN net load curve, on the loading of boundary transformations and the associated challenges. The study points out the number of substations that present the possibility of reverse flow of active power. 

One of the main conclusions in this scenario of expansion of generation directly connected to the distribution networks is the need for distributors to take on a more active role, acting as distribution system operators (DSOs) and in a coordinated manner with the ONS. This role is essential to ensure the efficiency and safety of the SIN operation in a context of increasing decentralization of generation resources.

The main figures presented indicate that the forecast for maximum load demand for the SIN, in 2029, is 120 GW, an increase of 12% compared to that seen in 2024. The installed generation capacity should reach, in December 2028, 251,6 GW, of which 57,6 GW refer to centralized wind and solar photovoltaic plants. 

The prospect of accelerated energy demand, driven by the expansion of segments such as green hydrogen and data centers, brings challenges for SEB, as well as opportunities. The profile of the national electricity matrix, with around 90% of its energy generated by renewable sources, has made the country attractive for the installation of data center projects used in Artificial Intelligence services, for example. 

The projects present a constant and high consumption profile at all times and days, and investors have expressed interest in connecting to the system in the PAR/PEL 2024 horizon.

The study provides, in a preliminary manner, a list of actions necessary to meet the initial integration demands, highlighting the need for improvements throughout the process of connecting large blocks of cargo, to support the safety and efficiency of the system in the face of the rapid transformations underway.

About PAR/PEL

The SIN Medium-Term Electrical Operation Plan – PAR/PEL aims to evaluate the SIN's performance, over a five-year horizon, so that future operations are carried out with adequate levels of safety, in compliance with the reliability criteria established in the Grid Procedures.

According to the ONS, the plan contains the indications of works necessary to fully meet demand, integrate new generating plants and ensure the operation of the electricity sector in the medium term. The Executive Summary of PAR/PEL 2024 is available on the ONS website, in the section “Energy in the Future – Electric Supply”.

all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.

CS Consulting ONS (National Electric System Operator) proper planning Brazilian electric sector
Photo by Mateus Badra
Mateus Badra
Journalist graduated from PUC-Campinas. He worked as a producer, reporter and presenter on TV Bandeirantes and Metro Jornal. He has been following the Brazilian electricity sector since 2020.
PreviousPrevious
NextNext

Leave a comment Cancel reply

Your email address will not be published. Required fields are marked with *

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

News from Canal Solar in your Email

Posts

Solar was fundamental to Mirassol's cash flow, says the club's board.

Solar was fundamental to Mirassol's cash flow, says the club's board.

MS confirms three mega solar power plants in partnership with Casa dos Ventos.

MS confirms three mega solar power plants together with Casa dos Ventos.

More news

Read More
Energy load in the SIN (National Interconnected System) falls 1,5% in September, says ONS (National System Operator).
  • November 14, 2025
Photo by Raphael Guerra
Raphael Guerra

Energy load in the SIN (National Interconnected System) falls 1,5% in September, says ONS (National System Operator).

Canal Solar - Solar power generation can increase by up to 20% with equipment cleaning and maintenance.
  • November 13, 2025
Photo by Henrique Hein
Henrique Hein

Solar power generation can increase by up to 20% with equipment cleaning and maintenance.

ANEEL approved all concession renewals for distributors analyzed in 2025.
  • November 12, 2025
Photo by Antonio Carlos Sil
Antonio Carlos Sil

ONS projects water storage levels 25% below 2025 levels in an unfavorable scenario.

It is a news and information channel about the photovoltaic solar energy sector. Channel content is protected by copyright law. Partial or total reproduction of this website in any medium is prohibited.

Facebook X-twitter Instagram Youtube LinkedIn Spotify

Site Map

Categories

  • News
  • Articles
  • Interviews
  • Consumer Guide
  • Authors
  • Projects
  • Brazil
  • World
  • Technical Articles
  • Opinion Articles
  • Manufacturer Items
  • Electrical Sector
  • Biddings
  • Products

Channels

  • About Us
  • Contact
  • We’re hiring!
  • Privacy
  • Expedient
  • advertise here

Membership and certifications

Copyright © 2025 Canal Solar, all rights reserved. CNPJ: 29.768.006/0001-95 Address: José Maurício Building – Mackenzie Avenue, 1835 – Floor 3, – Vila Brandina, Campinas – SP, 13092-523

We use cookies to make your experience on this site better Find out more about the cookies we use or turn them off in your .

Receive the latest news

Subscribe to our weekly newsletter

Canal Solar
Powered by  GDPR Cookie Compliance
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Cookies strictly required

Strictly Necessary Cookie should be at all times so that we can save your preferences for cookie settings.

Cookies for third parties

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.