Problems in transporting large photovoltaic modules

Hi-MO 5 bifacial module breakage rate is generally lower compared to that of larger modules
Produtos Hi-MO 5 da Longi são projetados para apresentar uma margem operacional de 10 cm para carga e descarga de contêineres
Longi's Hi-MO 5 products are designed to have an operating margin of 10 cm for loading and unloading containers

China is widely recognized as the world's manufacturing center for photovoltaic modules, shipping to all corners of the globe by sea, road, rail and air. 

With factors such as delivery cycle, capacity and cost to consider, sea transport has become the preferred mode for shipping and with this being the case, maximizing container capacity utilization is now a subject receiving great market attention. 

1) Packaging methods for photovoltaic modules

Vertical packaging is commonly seen as the ideal method, due to problems with the horizontal stacking alternative. 

Vertical packaging solves the three main problems of horizontal stacking, namely module frame deformation, glass breakage and invisible cracks caused in transit, and the vertical landscape solution has become the common choice over the portrait alternative.

Figura 1. Três métodos de embalagem para módulos fotovoltaicos: a) A embalagem vertical em paisagem é reconhecida como ótima; b) O empilhamento horizontal foi eliminado; c) A embalagem vertical no modo retrato é aplicada para módulos fotovoltaicos maiores
Figure 1 – Three packaging methods for photovoltaic modules: a) Vertical landscape packaging is recognized as optimal; b) Horizontal stacking has been eliminated; c) Vertical packaging in portrait mode is applied for larger PV modules.

2) Maximum size allowed with vertical packaging

Meeting the ultimate objective of reducing the proportion of broken products or products with invisible cracks upon arrival, vertical landscape packaging has a lower center center with the consequent lower risk of modules tipping over during packaging and unpacking, due to its design-for-performance advantage of operational security. 

This is the main reason for its preferential status, better meeting the requirements of reliability in maritime transport, packaging stability and safety of the employees involved. According to the door height of a container, the maximum allowable height for ideal packaging can be determined. The logical relationship is shown below:

Figura 2. Imagens do transporte do módulo fotovoltaico, localização da carga e descarga: a) O produto Hi-MO 5 é carregado no contêiner na fábrica, com uma margem de operação da empilhadeira de cerca de 10 cm; b) o contêiner é entregue em um local com terreno irregular; c) os módulos empilhados verticalmente com a orientação paisagem podem ser colocados de forma estável em diferentes situações
Figure 2 – Images of photovoltaic module transport, loading and unloading location: a) The Hi-MO 5 product is loaded into the container at the factory, with a forklift operating margin of around 10 cm; b) the container is delivered to a location with uneven terrain; c) vertically stacked modules with landscape orientation can be placed stably in different situations.

3) Questions about vertical stacking in portrait mode for large modules

The operating margin for loading and unloading containers is extremely limited, theoretically with only about 7 cm available. Longi's Hi-MO 5 products are designed to have an operating margin of 10 cm for loading and unloading containers.

However, this redundancy in operating height for larger modules in a vertical packaging scenario is reduced to about 7 cm once the height, packaging paper thickness and pallet height are taken into account, which means the total height will exceed 2.5m – and the container door is 2.575m. 

Although tightly packaged goods can be loaded and unloaded by skilled workers in a factory environment with equipment such as a loading dock, there are no such facilities available in overseas warehouses or on project sites.

Workers are at greater risk of injury when turning packages that are heavier and have a higher center of gravity. Compared to the weight of the bifacial Hi-MO 5 of 32.3 kg, the weight of a larger module exceeds 38.7 kg, an increase of almost 20%. 

Larger modules are also packaged via the vertical method in portrait format, which means the package height will exceed 2.5 m (see Figure 5a). The barycenter height is almost double compared to the Hi-MO 5, increasing the possibility of tipping over and subsequent injury.

Figura 3. Para evitar o tombamento da embalagem vertical, é necessário um suporte anti-capotamento e centenas de quilogramas de contrapeso, o que é difícil de obter no local do projeto
Figure 3 – To prevent the vertical package from tipping over, an anti-tip support and hundreds of kilograms of counterweight are required, which is difficult to obtain at the project site

Taking an initial tilt angle of 75° as an example, the weight of the largest module is 38.7 kg, with a 31-unit pallet having an overall gravity as shown below:

G = 38.7 × 31 × 9.8 ≈ 11760 N

The pressure on the beveled side of the support:

F = G × cos 75° ≈ 3043 N

The coefficient of static friction between the support and the sand is considered 0.4, with its equilibrium relationship with the horizontal force as follows:

Fmax = (Msupport × 9.8 + F × cos 75°) × 0.4 ≥ F × sin 75°

As per the above, the weight of the support must reach over 660 kg to maintain non-slip status, with the use of a support of this weight in a project with larger modules being a challenge during the construction and installation phases.

The weight of the stand can also be calculated under different tilt angles. The smaller the unpacking angle, the greater the risk of the support slipping.

If an installer is unpacking, the modules can also be turned by the wind reaching the fifth scale when the number to be unpacked is less than 10 units and the tilt angle is greater than 85° (e.g. figure 4.)

In summary, larger packaged modules stacked vertically in portrait orientation are at greater safety risk, with additional limitations in terms of unpacking in ground-mounted PV plants.

Figura 4. Diagrama esquemático de desempacotamento dos módulos no método vertical na orientação retrato, com suporte contra vento
Figure 4 – Schematic diagram of unpacking the modules in the vertical method in portrait orientation, with wind support

During the initial stage of construction of a large-scale ground-mounted photovoltaic plant, care must be taken to position the packaged modules to prevent them from tipping over, which makes traction more difficult on uneven terrain.

Compared to the weight per pallet of Hi-MO 5 bifacial modules, that of the larger modules shows an increase of 20%, resulting in a net weight of over 1.2 tonnes.

For this reason, a forklift or lifting machinery with a large load capacity is required for safe transportation, increasing labor and equipment costs to complete the installation within the construction period. When installing larger modules, there is also the possibility of lower efficiency and a higher rate of invisible cracks.

As shown in Figure 5b, it may be difficult for workers to handle a larger module, needing to place a corner on the ground, with the added concern of exceeding the recommended maximum weight of just under 35 kg for two-person handling (the maximum weight for handling by one person is 20 kg to 25 kg, with the coefficient for two people 0.666, i.e. 25 × 2 × 0.666 = 33.3 kg – see HSL Guide for Weight Limit in Manual Handling).

Figura 5. Desembalagem e instalação de módulos maiores: a) A altura da embalagem é muito maior do que a do instalador; b) O tamanho é muito grande e largo, levando a uma menor eficiência de instalação e uma taxa de quebra potencialmente maior
Figure 5 – Unpacking and installation of larger modules: a) The height of the packaging is much greater than that of the installer; b) The size is too large and wide, leading to lower installation efficiency and a potentially higher breakage rate.

According to research, the breakage rate of Hi-MO 5 bifacial module is generally lower compared to that of larger modules during installation, while the invisible cracking rate for larger modules increases by more than five times.

In conclusion, LONGi adheres to the proven reliability of vertical landscape packaging solution for its Hi-MO 5 modules, this minimizing shipping costs and making unpacking and installation more convenient for on-site workers.

Picture of Equipe de Engenharia do Canal Solar
Solar Channel Engineering Team
Solar Channel Engineering Team

One Response

  1. Great article. I contracted for the purchase/installation of a photovoltaic kit, with 20 panels of 560 W each, for my home. I try to read everything I can find about solar panels and how to avoid damaging them. What is the MAXIMUM TORSION that modules can be subjected to without damage?

Leave a Reply

Your email address will not be published. Required fields are marked *

Related News

Receive the latest news

Subscribe to our weekly newsletter