New production projects are reshaping the natural gas map in Brazil.

Expansion of national production will be accompanied by greater participation from the Northeast region, demand for thermoelectric plants, and R$ 15,9 billion in investments.

Canal Solar - New production projects reshape the natural gas map in Brazil.

Photo: Disclosure/Petroarm

The potential supply of natural gas produced in Brazil is expected to increase from 61 million to 112 million cubic meters per day (MMm³/day) between 2026 and 2036, a growth of over 80%.

The expansion will be driven primarily by the start-up of new production projects, most notably Raia in Rio de Janeiro and SEAP (Sergipe Deep Waters).

Despite the prospect of increased availability, utilizing this volume will depend on investments in transportation and processing to overcome limitations in existing infrastructure.

These projections are part of the Natural Gas Notebook of the PDE (Ten-Year Energy Expansion Plan) 2036, published by the MME (Ministry of Mines and Energy) and EPE (Energy Research Company).

The study estimates approximately R$ 15,9 billion in investments in the gas supply chain over the analyzed period and points to important changes in the regional distribution of supply and in the sources of supply.

Northeast expands participation

Rio de Janeiro is expected to remain the leading producing state, but the participation of other regions is likely to increase.

The Raia project is scheduled to begin operating in 2028, while Sergipe Águas Profundas is expected to start contributing in 2030. In Maranhão, the potential of the Parnaíba Basin could also increase supply.

With these changes, the Northeast's share of the national potential supply should rise from 19% in 2026 to 34% in 2036.

By the end of the period, 81% of the potentially available gas in the country should be connected to the integrated transportation network, while the remaining 19% will be associated with the isolated systems of Urucu and Maranhão.

Taking imports into account as well, the total potential supply in the integrated network should increase from 132 MMm³/day to 175 MMm³/day, an increase of over 30%.

The pre-salt layer will continue to be the main source of national gas in this system, with an average share of close to 74% during the period.

Imports

The plan foresees a significant reduction in the volume of Bolivian gas transported through the Bolivia-Brazil Gas Pipeline (GASBOL). The projection drops from 13 MMm³/day in 2026 to 5 MMm³/day starting in 2030.

The document emphasizes, however, that the gas pipeline has a handling capacity of approximately 30 MMm³/day, which could be utilized if there is an expansion of infrastructure and supply from Bolivia or Argentina.

In the case of LNG (liquefied natural gas), import capacity is expected to increase at the beginning of the horizon, with the start of operations at the Suape terminal in Pernambuco and the resumption of activities at the TRSP (São Paulo Regasification Terminal). After this initial movement, the projected regasification capacity remains relatively stable.

The PDE also considers that the contracting of new thermal power plants in the 2026 Capacity Reserve Auction could stimulate the implementation of other LNG terminals.

The import capacity, therefore, may still be revised in future editions of the plan, as information about these projects becomes available.

Thermal power plants drive demand

Total expected natural gas consumption in the country is projected to grow from 71 MMm³/day in 2026 to 104 MMm³/day in 2036, equivalent to an average annual expansion of 3,8%.

When considering peak demand, which assumes the full operation of gas-fired power plants, the volume increases from 154 to 244 MMm³/day, almost 60% in ten years.

Thermal power generation is the main component of this peak demand, with the potential need of power plants increasing from 96 to 164 MMm³/day, a growth of over 70%, concentrated especially between 2027 and 2031, a period in which several units contracted under LRCAP 2026 are expected to come online.

The projected average consumption for thermal power plants, however, is much lower, specifically from 14 MMm³/day in 2026 to 25 MMm³/day in 2036.

The difference highlights the role of gas as a backup and complementary fuel, with greater use during times when the electrical system needs additional generation.

In other sectors — industry, commerce, residential and transport — demand is expected to increase from 40 to 55 MMm³/day.

The downstream sector, which includes refineries and nitrogen fertilizer plants, will reach 22 MMm³/day in 2036, driven by expansions in refining, the Boaventura Energy Complex, and the resumption or implementation of fertilizer units.

Bottlenecks can limit the utilization of the offer.

Even with potential supply exceeding projected demand throughout the period, the study warns that this surplus does not mean guaranteed physical availability in all regions. Simulations identified constraints in the three evaluated subsystems of the integrated grid.

In the Northeast, the growth in production and consumption, especially from new thermoelectric plants, will require improvements in transportation between Alagoas and Pernambuco, including the duplication of gas pipelines and an increase in compression capacity.

In the Southeast, expansions will be necessary to better utilize the pre-salt gas and transfer it to other regions, compensating for the reduction in Bolivian supply.

In the Central-West, São Paulo, and South regions, the need involves expanding pipelines and compressors to overcome limitations in the final stretch of GASBOL and allow the receipt of gas from the Southeast and LNG through the Gás Sul Terminal in Santa Catarina.

The R$ 15,9 billion foreseen in the PDE (Energy Development Plan) covers, among other projects, the Raia and Sergipe Deep Waters outflow pipelines, the Suape terminal, new compression stations, and the Natural Gas Processing Unit (UPGN) in Miranga, Bahia.

The National Integrated Plan for Natural Gas and Biomethane Infrastructure (PNIIGB) will provide further details on alternatives to overcome bottlenecks and integrate gas and biomethane infrastructure.

all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.

Antonio Carlos Sil
About the Author
Antonio Carlos Sil

Antonio Carlos Sil is a journalist graduated from FMU/FIAM. He worked as a reporter for Brasil Energia, in addition to providing services to Agência Estado, Exame and Canal Energy. Worked in communications consultancies for CPFL Energia, CESP and AES Tietê. Has covered the electricity sector since 2000. Has experience covering events such as energy auctions, conventions, lectures, fairs, congresses and seminars.

Comments

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.