Cemig publishes new criteria for analyzing DG connections

Changes involve consumers in the residential, rural and commercial classes, with loads of up to 50 kW

Cemig publishes new criteria for analyzing DG connections

Photo: José Cruz/Agência Brasil

A cemig (Minas Gerais Energy Company) announced, this Thursday (14), which started to adopt new parameters technical analysis for evaluating DG connections (distributed generation) for consumers low voltage for residential, rural and commercial classes, with load up to 50 kW.

The new criteria have immediate validity and, according to the company, will enable the expansion of connections in this modality, as long as there is no risk to other customers and the distributor's system.

The new criteria adopted are divided into three items:

Item 1: In the case of a request for local micro DG without flow reversal, the analysis will be carried out in accordance with REN 1.000, without applying Art. 73 of the standard.

Item 2: For requests for local micro DG in consumer units with billing in the last 12 months and indication of flow reversal, the customer will have the options listed in §1 of Article 73 of REN 1.000. Especially in relation to the possibility of reducing the injected power, the customer's consumption history over the last 12 months will also be analyzed to release the local micro DG connection up to the limit of their profile.

Item 3: The new criteria also cover the case of requests for local micro DG for new consumer units or units with less than 12 months of billing, with an indication of flow reversal. As it is a new consumer unit with no consumption history or that does not have a 12-month billing history, the same provisions in item 2 apply. However, the release of the local micro GD connection will consider the average consumption of the class and load factor based on the results of the measurement campaign from the last tariff review process.

Resolution No. 1.000

According to Cemig, the new criteria adopted by the company come ahead of the discussions on updating the regulations set out in the technical note of ANEEL (National Electric Energy Agency) which deals with the topic, in light of Aneel Normative Resolution No. 1.000 (REN 1000), which establishes the rules for providing the public electricity distribution service.

“It is important to highlight that analyzes of technical conditions will be maintained regarding severe impacts on the distribution network, which could degrade the quality of supply or compromise operational safety,” said Marney Tadeu Antunes, director of Cemig.


all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.

Henrique Hein
About the Author
Henrique Hein

He worked at Correio Popular and Rádio Trianon. He has experience in podcast production, radio programs, interviews and reporting. Has been following the solar sector since 2020.

Comments (1)

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

  • THIAGO HENRIQUE

    Good afternoon. I have a client who, according to the new criteria adopted, is fully compliant with the Cemig network's flow reversal guidelines, as their average 12-month consumption falls under item 2. The installed solar power plant is 31kW. However, Cemig placed a restriction simply because the client has a standard circuit breaker in operation of 3 x 800A, which exceeds the 50kW load limit.

    My question is: According to Cemig's ND 5.1 standard, a released load of 50kW requires a circuit breaker of up to 3 x 150A. So, if there's an electrical panel with a circuit breaker above 150A released for the load, can Cemig block it and impose a flow reversal restriction, even knowing that there won't be a reversal based on the calculations of the new adopted criteria? I don't understand this and haven't received a response from Cemig yet.

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.