A ANEEL (National Electric Energy Agency) decided, this Tuesday (4), the maintenance of the fine of R$ 28,3 million for the Light distributor. O resource was denied during a collegiate meeting.
Light was penalized on March 5 this year due to the delay in power restoration electricity in interruptions in the period between October 2022 e September 2023 in the distributor's concession area.
During the period analyzed, inspection detected recovery time more than 24 hours in 39.930 interruptions, which harmed 77.651 consumers.
According to the analysis, there was a significant worsening compared to 2020 when 16.689 outages were restored over 24 hours, affecting 42.389 consumers
all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.
Comments (1)
Comments are moderated before publication.Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.
Power to electrical energy, with this we must consider better conditions for the consumption of the work carried out.