O ONS (National Electrical System Operator) registered, in this Monday, at 14h17, um new record na instant demand de load do without (National Interconnected System), the landing was from 100.955 MW.
According to the ONS, it was the first time in the history of the SIN that the load surpassed the 100.000 MW mark, previously the mark was 97.659 MW, measured on September 26, 2023.
Also according to the ONS, at the time the new level was registered, the load was served by 61.649 MW of hydraulic generation (61,1%); 10.628 MW of thermal generation (10,5%); 9.284 MW of wind generation (9,2%); 8.505 MW of centralized solar generation (8,4%); and 10.898 MW of solar generation from MMGD (micro and mini distributed generation) of 10,8%.
According to the Operator, the main reason for this record load is the large increase in temperature in much of Brazil.
In addition to the SIN, the SE/CO subsystem also reached a new load level, surpassing the 60.000 MW mark for the first time, at 15:30 pm, the Southeast/Central-West load reached an impressive peak of 60.735 MW.
The best load index for the subsystem so far was 57.791 MW, which occurred at 14:30 pm on September 26, 2023.
Read more: https://canalsolar.com.br/calor-faz-disparar-demanda-de-energia-eletrica-em-novembro/
Comments
Comments are moderated before publication.Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.