• Sun, December 7, 2025
Facebook X-twitter Instagram Youtube LinkedIn Spotify
  • GC Solar: 17,95 GW
  • GD Solar: 41,3 GW
  • TOPCon Modules: $0,088/W
  • P-Type Cells: $0,034/W
  • N-Type Cells: $0,032/W
  • HJT Modules: $0,10/W
  • N-Type Wafer: US$0,128/pc
  • Polysilicon: US$ 19,00/kg
  • GC Solar: 17,95 GW
  • GD Solar: 41,3 GW
  • TOPCon Modules: $0,088/W
  • P-Type Cells: $0,034/W
  • N-Type Cells: $0,032/W
  • HJT Modules: $0,10/W
  • N-Type Wafer: US$0,128/pc
  • Polysilicon: US$ 19,00/kg
  • advertise here
  • About us
  • Expedient
logo site solar channel
  • News
    • energy storage
    • Market and Prices
    • Investments & Business
    • Policy and Regulation
  • Articles
    • Batteries
    • Photovoltaic structures
    • Photovoltaic inverters
    • Opinion
  • Renewable
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Events
  • Videos
  • Electric Vehicles
  • Consultancy
  • Recent
  • News
    • energy storage
    • Market and Prices
    • Investments & Business
    • Policy and Regulation
  • Articles
    • Batteries
    • Photovoltaic structures
    • Photovoltaic inverters
    • Opinion
  • Renewable
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Events
  • Videos
  • Electric Vehicles
  • Consultancy
  • Recent
  • News
    • Brazil
    • World
    • Technology and inovation
  • Articles
    • technicians
    • Opinion
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • Events
  • Videos
  • About Us
  • Advertise Here
  • CS Consulting
  • Canal VE
  • Recent
  • News
    • Brazil
    • World
    • Technology and inovation
  • Articles
    • technicians
    • Opinion
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • Events
  • Videos
  • About Us
  • Advertise Here
  • CS Consulting
  • Canal VE
  • Recent
logo site solar channel
Home / News / TCU points out government failures in combating the energy crisis

TCU points out government failures in combating the energy crisis

Federal Court of Accounts assesses that the measures adopted were taken without estimating tariff impacts
Follow on Whatsapp
  • Photo by Mateus Badra Mateus Badra
  • January 17, 2022, at 07:00 AM
4 min 12 sec read

The TCU (Federal Audit Court) concluded that there is no strategic contingency plan for critical situations, on the part of the government and bodies in the electricity sector, to face the energy crisis.

According to the Audit, the measures adopted were taken in a “hasty” manner, with little predictability and no estimate of tariff impacts on the consumer.

“Flaws were found in the planning of actions, which focused on increasing energy supply, without due attention to measures to reduce demand,” said the TCU report, authored by Minister Benjamin Zymler.

Furthermore, the Authority identified that there was no investigation of the structural and cyclical causes that contributed to the hydroenergy crisis.

The conclusions are part of an inspection carried out by the Court to monitor and evaluate the government's actions in the face of the 2020/2021 energy crisis. Monitoring was carried out between June and December 2021.

The MME (Ministry of Mines and Energy), in response to such considerations from the TCU, commented that it is analyzing the report and is in conversations with the court to clarify all the issues raised.

Failures

In addition to the flaws highlighted in the execution and communication of the measures adopted from a demand perspective, a failure was reported in the simplified and emergency energy auction, which contracted energy at a cost of R$39 billion. According to the Audit, it was carried out in a shorter time than would be recommended.

“Incurring several risks to its success, considering that the schedule
forecast indicated that the winners should sign their contracts in November 2021 to put the projects into operation on 01/05/2022”, the report pointed out;

Penalized consumer

Regarding the estimation of tariff impacts of the measures adopted to face the crisis, it was verified that the impact of the decisions taken so far implies a high cost for the consumer.

Furthermore, it was found that the measures were implemented without the necessary advance prediction of the tariff impacts on consumers.

As reported by Canal Solar, the Government's emergency actions to avoid energy rationing, for example, culminated in increase in electricity bill of Brazilians.

In understanding the ANEEL (National Electric Energy Agency), the adjustment was necessary to compensate for the cost of exceptional measures, such as activating thermal power plants.

Read more: Electricity bill will be more expensive in 2022, reports ANEEL

In fact, this increase, driven by the water crisis, should cause the loss of around 290 thousand jobs in 2022, according to a study published by the CNI (National Confederation of Industry).

MP 1.078 / 2021

The TCU also commented that it was necessary to remember that the MP 1.078 / 2021 not only authorized the contracting of a financial operation to cover financial impacts arising from the situation of water scarcity, “but also included in its scope deferrals applied in tariff processes prior to the release of resources from the financial operation”.

“Consequently, in some way, an accumulation of tariff increases is beginning to form due to previous tariff processes, the Covid Account and decisions taken during the hydroenergy crisis”, added the research.

Structural causes

Regarding structural causes, the audit team said that on repeated occasions, it questioned those responsible about the reasons – in addition to negative hydrology – that contributed to the worsening of the crisis.

“However, the responses demonstrated that there has not yet been a detailed study on the matter, nor is there a consensus on the subject, which could make it difficult to successfully identify the necessary interventions to be carried out and a supervening public policy for the sector”, they emphasized.

Determinations and recommendations to the MME

The Federal Court of Auditors, at the end of the report, gave some determinations and recommendations to the MME.

Determinations

  • Develop a strategic contingency plan to face hydro-energy crises;
  • Prepare a study to identify and propose solutions for the causes that led to the risk of imbalance between energy demand and supply;
  • Present an assessment of the advantage of a new credit operation for distributors when using RTEs (Extraordinary Tariff Revisions) and carry out a study on the advantage of including tariff deferrals;
  • À ANEEL, define a mechanism that has the “ability to maintain an economic signal of the price of energy for the consumer of electrical energy”.

Recommendations

  • To the MME, carry out a study to individually evaluate the cost-effectiveness and effectiveness of the measures adopted to face the crisis and evaluate the results obtained by the Incentive Program for the Voluntary Reduction of Electricity Consumption, in particular regarding billing errors that may have been committed;
  • À ANEEL, to analyze the results of the Voluntary Consumption Reduction Program using concepts of behavioral economics.
energy crisis water crisis Grounding and SPDA Course Market and Regulation Course failures government measures TCU
Photo by Mateus Badra
Mateus Badra
Journalist graduated from PUC-Campinas. He worked as a producer, reporter and presenter on TV Bandeirantes and Metro Jornal. He has been following the Brazilian electricity sector since 2020.
PreviousPrevious
NextNext

Leave a comment Cancel reply

Your email address will not be published. Required fields are marked with *

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

News from Canal Solar in your Email

Posts

Automation in buildings can save the equivalent of an Itaipu hydroelectric dam annually, study shows.

Automation in buildings can save the equivalent of an Itaipu hydroelectric dam annually, study shows.

Data centers will double energy consumption in Brazil in four years.

Data centers will double energy consumption in Brazil in four years.

More news

Read More
Experts see intervention by Enel São Paulo as unlikely.
  • December 5, 2025
Photo by Antonio Carlos Sil
Antonio Carlos Sil

Experts see intervention by Enel São Paulo as unlikely.

Canal Solar - Enel-SP at risk of potential federal intervention.
  • December 2, 2025
Photo by Antonio Carlos Sil
Antonio Carlos Sil

Enel-SP at risk of potential federal intervention.

Aerial image of a solar farm.
  • November 17, 2025
Photo by Mateus Badra
Mateus Badra

Solar farm: what is it and how does it work?

It is a news and information channel about the photovoltaic solar energy sector. Channel content is protected by copyright law. Partial or total reproduction of this website in any medium is prohibited.

Facebook X-twitter Instagram Youtube LinkedIn Spotify

Site Map

Categories

  • News
  • Articles
  • Interviews
  • Consumer Guide
  • Authors
  • Projects
  • Brazil
  • World
  • Technical Articles
  • Opinion Articles
  • Manufacturer Items
  • Electrical Sector
  • Biddings
  • Products

Channels

  • About Us
  • Contact
  • We’re hiring!
  • Privacy
  • Expedient
  • advertise here

Membership and certifications

Copyright © 2025 Canal Solar, all rights reserved. CNPJ: 29.768.006/0001-95 Address: José Maurício Building – Mackenzie Avenue, 1835 – Floor 3, – Vila Brandina, Campinas – SP, 13092-523

We use cookies to make your experience on this site better Find out more about the cookies we use or turn them off in your .

Receive the latest news

Subscribe to our weekly newsletter

Canal Solar
Powered by  GDPR Cookie Compliance
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Cookies strictly required

Strictly Necessary Cookie should be at all times so that we can save your preferences for cookie settings.

Cookies for third parties

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.