Vertex 660 W reduces CAPEX and LCOE by up to 9%

Black & Veatch, a global service provider for PV projects, highlighted the advantages of Trina's 660 W panels

07-02-22-canal-solar-Vertex 660 W reduces CAPEX and LCOE by up to 9%

Vertex 210–660 W achieves additional cost-saving benefits. Photo: Trina Solar/Disclosure

Since the launch of the 600 W+ series from Trina Solar, international third-party organizations have evaluated and studied the advantages of BoS (Balance of System) and LCOE (Levelized Cost of Energy) of Vertex modules.

Most recently, Black & Veatch, an independent global solar project services provider, completed a CAPEX and LCOE assessment, comparing new generation ultra-high power 210mm wafer size photovoltaic modules to 182mm wafer size panels. mm, 158 mm and 166 mm.

The results show that, compared to the 166 mm 450 W module, the 210 mm 660 W module reduces CAPEX and LCOE by more than 9%. Compared to the 182 mm and 535 W panels, the 210 mm and 660 W panels reduce CAPEX by up to 4,58% and LCOE by up to 3,94%.

Additionally, Trina Solar's 158 Wp 84-480 cell layout performs better than the standard 166-72 cell format regarding CAPEX and LCOE savings.

In terms of cost difference, the increased value is mainly due to the reduced BoS values. According to Trina, BoS prices are impacted by module chain length, overall module power, and the number of PV panels required to meet the constant capacity assumption made throughout the hypothetical projects.

“A plan using a panel with a lower power will require more modules and, therefore, will have higher BoS costs, including additional values ​​for cultivated area, location, cleaning and classification, number of racks and cabling, for example,” said the company in note.

The 210-660 W required the fewest modules to reach the project's hypothetical capacity of 100 MWac (125 MWdc), with 88.383 fewer panels needed. This equates to savings of up to 32%, stated the manufacturer.

Compared to 166-450W modules, the Vertex 210–660W achieves additional cost-saving benefits across the board:

  • BoS material: US$1,6 million;
  • BoS installation: U$$ 979 thousand;
  • Rack and post installation: US$1,8 million;
  • Construction overhead: US$1,9 million;
  • Administrative and EBT: US$ 1,1 million;
  • Total initial cost CAPEX: US$9,6 million.
Mateus Badra
About the Author
Mateus Badra

Journalist graduated from PUC-Campinas. He worked as a producer, reporter and presenter on TV Bandeirantes and Metro Jornal. He has been following the Brazilian electricity sector since 2020.

Comments

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.