• Friday, June 26, 2026
Facebook X-twitter Instagram Youtube LinkedIn Spotify
  • GC Solar: 22,33 GW
  • GD Solar: 48,33 GW
  • advertise here
  • About Us
  • Expedient
logo site solar channel
  • News
    • Market & Investments
    • International market
    • Politics & Regulation
    • Projects & Applications
    • Renewable
    • Sustainability & ESG
    • Technology & Innovation
    • Electric Vehicles
  • Articles
    • Opinion Article
    • Manufacturer's Article
    • Technical Article
  • Latam
  • Batteries
  • Blog
  • Solar Energy Companies
    • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Firmare
  • Courses
  • News
    • Market & Investments
    • International market
    • Politics & Regulation
    • Projects & Applications
    • Renewable
    • Sustainability & ESG
    • Technology & Innovation
    • Electric Vehicles
  • Articles
    • Opinion Article
    • Manufacturer's Article
    • Technical Article
  • Latam
  • Batteries
  • Blog
  • Solar Energy Companies
    • Integrators
  • Magazine
    • Magazine Canal Solar
    • Conecta Magazine
  • Firmare
  • Courses
  • News
    • Market & Investments
    • International market
    • Politics & Regulation
    • Projects & Applications
    • Renewable
    • Sustainability & ESG
    • Technology & Innovation
    • Electric vehicles
  • Articles
    • Opinion
    • technicians
    • Manufacturer Items
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • About Us
  • Advertise Here
  • CS Consulting
  • Courses
  • International market
  • News
    • Market & Investments
    • International market
    • Politics & Regulation
    • Projects & Applications
    • Renewable
    • Sustainability & ESG
    • Technology & Innovation
    • Electric vehicles
  • Articles
    • Opinion
    • technicians
    • Manufacturer Items
  • Latam
  • Blog
  • Solar Energy Companies
  • Integrators
  • Magazine
    • Conecta Magazine
  • About Us
  • Advertise Here
  • CS Consulting
  • Courses
  • International market
logo site solar channel
Home / Articles / Opinion Article / Can I correct the access request and stick to the old GD rules?

Can I correct the access request and stick to the old GD rules?

The approval process can be considered one of the most controversial in the electricity sector
Follow on Whatsapp
  • Photo by Pedro Dante Pedro Dante
  • February 14, 2023, at 13:06 PM
5 min 55 sec read
Canal Solar Can I correct the access request and remain within the old GD rules?
Close to the deadline, there was a boom in requests for access opinions

With the collaboration of Renato Edelstein e Leonardo Balbino*

On February 7, 2023, more than a year after the sanction of Law No. 14.300/22, considered the Legal Framework for GD (distributed generation), the ANEEL (National Electric Energy Agency) approved the improvement of the rules applicable to MMGD (micro and mini distributed generation).

The approval process can be considered one of the most controversial in the recent history of the electricity sector.

Within the scope of the public consultation that dealt with the topic, more than 800 contributions were received and the deliberation of the topic by the Board of ANEEL took more than 15 hours.

Among many other points that have generated a lot of debate, there is a legal issue that deserves special attention in our opinion, due to a possible significant impact on access requests made until January 7, 2023.

This point concerns the deadline for correcting the access request to obtain full MMGD benefits.

In effect, the full benefits of MMGD (application of the rule plus compensation benefit) will only be applicable to interested parties who file an access request with the distributor within 12 months from the publication of this Law, that is, January 7, 2023.

Given this scenario, close to the deadline, there was a boom in requests for access opinions and project delivery commitments.

This is a fact that can be seen positively as it means that entrepreneurs have assimilated the window of opportunity for implementing DG projects.

Despite this, since the publication of the GD Legal Framework there was no complete clarity, and not even regulation of the ANEEL, regarding what the requirements would be to consider that the mere request for access would guarantee entrepreneurs the so-called (and much desired) “acquired right” to full compensation until 2045, with the distributors themselves having a notable difficulty in dealing with the number of requests submitted.

Aware of this practical difficulty in analyzing access requests, the legislator himself made a point of providing that interested parties could make the access request with pending documents and remediable defects, with the expectation of being able to correct the documentation later.

This is because, article 2, § 4 of Law nº 14.300/22, provides that:

“in the event of a formal defect that can be remedied or a lack of documents in the accessor's responsibility studies necessary for the preparation of the projects that make up the access opinion, the accessed distributor will notify the accessor of all verified pending issues that must be resolved and filed with the accessed distributor within 30 (thirty) days from the date of receipt of formal notification from the distributor for this purpose, providing a different period agreed between the parties”.

In other words, the indication of the GD Legal Framework is precisely in the sense of the possibility of reorganizing the access request, without prejudice to the acquired right.

Despite the legal basis for making any corrections to the access request, the Board of Directors of ANEEL and the Federal Prosecutor's Office took a diametrically opposite direction and adopted an understanding that, in our view, directly violates the legal text and may be challenged by interested parties.

In this sense, the Board of ANEEL considered that user responsibility studies are no longer required since March 2022when Normative Resolution 1.000/2021 established that all studies became the responsibility of the distributor.

Therefore, in the current framework, there would be no “documents” or “studies” under the responsibility of the accessor that are not listed in the access request.

Thus, in line with the conclusions of the Federal Prosecutor's Office, set out in Opinion No. 00038/2023/PFANEEL/PGF/AGU, the possibility of using article 2, § 4 of Law No. 14.300/22 to create the possibility of classifying those who did not comply with the command of item II of art. 26, of not presenting documents relating to the complete and timely access request, was ruled out.

This is how the Federal Prosecutor's Office expressed itself: ANEEL in the aforementioned Opinion:

“The access request, as provided for in § 2, should have been made completely by January 7, 2023 to guarantee the application of article 26 of Law nº 14.300/2022. For the access request, there is no normative provision for its completion, but only the establishment of a deadline for the distributor to reject the request due to insufficient documents, which is in accordance with article 71 of REN nº 1.000/2021. And for this there is a reason: in favor of legal security, Law No. 14.300/2022 introduced a transition rule to maintain the rule previously in force for facilities already in operation and for those that had a complete access request by the 7th of January 2023. If any incomplete access request were allowed to be filed by January 7, 2023, this means that Law No. 14.300/2022 itself would be bringing an innocuous transition rule: the mere filing of any role in the distributor to remove the application of the tariff rule of Law No. 14.300/2022 until 2045.”

Thus, according to the position established by ANEEL, If documents or studies are pending, the user may not be entitled to full distributed generation benefits.

In this case, the project could fit into the transition rules, but not within the old and more beneficial system.

That is, the position of the ANEEL, in addition to violating the text of the Law and being able to be questioned, ratifies the importance of the protocol of the request for access opinion (connection budget) with all applicable requirements and documents. If any inconsistency is found, the “acquired right” may be affected.

This point is relevant in the context of M&As projects involving DG assets and deserves special attention according to the specific case.

This is because, if the acquired right is not achieved, the project's economics may not close, and there must be a prior analysis of the regularity of the access request.

If the position of the ANEEL, the mere protocol of the request for an opinion will not be sufficient for the purposes of guaranteeing the most beneficial compensation rule.

The access request protocol must be considered without any pending issues or reservations, which is only assessed after the analysis and positioning of the energy distributor.

The tendency is for the discussion to persist due to the various investments that have been and will be made in the distributed generation sector, and there must always be predictability and legal certainty for the development of projects.

 

* Lefosse energy area associates

Discover the Advanced Course on Solar Power Plant Design up to 3MW

ANEEL (National Electric Energy Agency) Microgeneration Course Legal Structuring Course board of directors of ANEEL structuring Law 14.300 / 2022 GD legal framework MMGD (micro and mini distributed generation)
Photo by Pedro Dante
Pedro Dante
Partner in the energy area at Lefosse Advogados. President of the Regulation Studies Committee of the Brazilian Institute for the Study of Energy Law. Coordinator of the Energy and Arbitration Committee of the Business Arbitration Chamber. Arbitrator at the Chamber of Measurement and Arbitration of Western Bahia. Effective member of the OAB/SP Energy Law Commission. Lawyer specializing in regulatory matters related to the electricity sector with over 19 years of experience in the sector.
PreviousPrevious
NextNext

Answers of 2

  1. Glauber Bazotti said:
    17 October 2023 to 11: 16

    And in the case of an increase in system power, for example, I approved a 10 Kwp system, but I want to increase it to 20 Kwp, what would happen in this situation?

    Reply
  2. Glauber Bazotti said:
    17 October 2023 to 11: 15

    And in the case of an increase in load, for example, I approved a 10 Kwp system, but I want to move to 20 Kwp, what would this situation be like?

    Reply

Leave a comment Cancel reply

Your email address will not be published. Required fields are marked with *

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

News from Canal Solar in your Email

Posts

Regarding the time slot reserved for agricultural flexibility.

Regarding the time slot reserved for agricultural flexibility.

Australia: the solar laboratory anticipating Brazil's challenges.

Australia: the solar laboratory anticipating Brazil's challenges.

More news

Read More
Energy storage as a regulated asset: what changes with the new resolution of ANEEL?

Energy storage as a regulated asset: what changes with the new resolution of ANEEL?

Canal Solar - Director of ANEEL Warning about the risk of a systemic blackout in Brazil. We are reaching that point.

director of ANEEL Warning about the risk of a blackout in Brazil: "We are reaching that point."

Broadcast revenues rise 9,4% to R$ 54,95 billion.

Broadcast revenues rise 9,4% to R$ 54,95 billion.

It is a news and information channel about the photovoltaic solar energy sector. Channel content is protected by copyright law. Partial or total reproduction of this website in any medium is prohibited.

Facebook X-twitter Instagram Youtube LinkedIn Spotify

Site Map

Categories

  • News
  • Articles
  • Interviews
  • Consumer Guide
  • Authors
  • Videos
  • Projects
  • Magazine
  • Electric Vehicles

Channels

  • About Us
  • Contact
  • Privacy
  • Quality Policy
  • Work with us
  • Expedient
  • advertise here

Membership and certifications

Copyright © 2026 Canal Solar, all rights reserved. CNPJ: 29.768.006/0001-95 Address: José Maurício Building – Mackenzie Avenue, 1835 – Floor 3, – Vila Brandina, Campinas – SP, 13092-523
Receive the latest news

Subscribe to our weekly newsletter

Fill in the information above and receive your free copy of Canal Solar magazine.