ONS must intensify use of thermal plants to meet maximum demand

CMSE recommended that ANP take the necessary measures to guarantee the gas supply

ONS must intensify use of thermal plants to meet maximum demand

Image: Disclosure/ONS

Despite the satisfactory levels of hydroelectric reservoirs at the end of the dry season, the ONS (National System Operator) faces difficulties in meeting the load during peak hours, between 18 pm and 20 pm.

At the CMSE (Electric Sector Monitoring Committee) meeting held on Wednesday (9), the ONS pointed out the need to intensify the use of thermoelectric plants, in addition to importing energy and making operational rules more flexible, to ensure demand is met between October and December.

The CMSE recommended to the ANP (National Agency of Petroleum, Natural Gas and Biofuels) the adoption of measures that ensure a regular supply of natural gas for the generation of electricity in the SIN (National Interconnected System).

CEMADEN (National Center for Monitoring and Alerts for Natural Disasters) reported that Brazil is facing the worst drought in recent years. ONS projections demonstrate uncertainty about the start of the wet season, although some models indicate more intense rainfall from the second half of October. 

“The Stored Energy (EAR) projections indicate that the Southeast/Central-West subsystem would reach, at the end of March 2025, in the most optimistic scenario, 13,8 pp above the storage verified in March 2024. In the most pessimistic scenario, the projection would be 23,4 pp below that recorded”, declared the ONS in a press release.

Daylight saving time will only be implemented if essential, says minister

ENA (Influent Natural Energy) estimates indicate values ​​below the MLT (Long Term Average) for the period from October 2024 to March 2025. Even so, the reservoir level in September was at 49%, considered adequate for the end of the dry season.

“With the severe drought of recent months, the first rains need to initially restore soil moisture so that flow levels can subsequently recover,” explained the Operator.

ONS creates operational plan to avoid power outages during elections

Don't miss any news from the electricity sector! Sign up to our Community by clicking here and get exclusive access to our content!

all the content of Canal Solar is protected by copyright law, and partial or total reproduction of this site in any medium is expressly prohibited. If you are interested in collaborating or reusing part of our material, please contact us by email: redacao@canalsolar.com.br.

Wagner Freire
About the Author
Wagner Freire

Wagner Freire is a journalist graduated from FMU. He worked as a reporter for Jornal da Energia, Canal Energy and Agência Estado. Covering the electricity sector since 2011. Has experience in covering events such as energy auctions, conventions, lectures, fairs, congresses and seminars.

Comments

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.