Equatorial Energia completes transmission project 21 months early

The company signed a contract for the Equatorial Transmissora SPE 1 project in February 2017, after winning the concession at auction

The Equatorial Energia group reported that an electricity transmission project began commercial operation this month, almost two years ahead of schedule. With the completion of the project, the company will have annual revenue of R$86,5 million from the operation and maintenance of the facilities.

The company signed a contract for the Equatorial Transmissora SPE 1 project in February 2017, after winning the concession at an auction held by the federal government and the ANEEL (National Electric Energy Agency).

According to the company, the project involved the construction of 251 km of lines in Bahia. In total, the budget was R$496 million.

Mateus Badra
About the Author
Mateus Badra

Journalist graduated from PUC-Campinas. He worked as a producer, reporter and presenter on TV Bandeirantes and Metro Jornal. He has been following the Brazilian electricity sector since 2020.

Comments

Comments are moderated before publication.

Comments should be respectful and contribute to a healthy debate. Offensive comments may be removed. The opinions expressed here are those of the authors and do not necessarily reflect the views of the author. Canal Solar.

Leave your comment

Canal Solar
Privacy

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.